Project included 3.5km of road re-construction, 7,000m of curb & gutter, 700m of concrete sidewalk, a roundabout, 3km of multi-use path, intersection improvements, street lighting, sewer and watermain construction, detention pond and landscape works. Scope: - Remove existing concrete and asphalt road - Reuse road concrete as base of multi-use pathway - Reconstruct road, curbs and gutters - Construct new detention pond - Lighting and signalized intersection - Landscaping