The scope of this project was to place two individual classes of aggregate to a total depth of 2.17 meters along the total length of the 2,000 LM of bored tunnel. We met multiple challenges, including:
24-hour, non-stop work
A conveying system and chute had to be installed to transfer aggregates from the stockpiles at ground level to the trucks below
All equipment had to be lowered into the portal with a 210 tonne crane
Height of the tunnel was insufficient for conventional trucks to dump so to facilitate moving the aggregate, we used Cat 730 articulate trucks with ejector boxes
Without room to turn, the 730 Cat trucks reversed into the tunnel with their load
A small dozer and compactor were used within the tunnel to place and compact the aggregate
Access was restricted to the north portal on the north end of the tunnel
The base of the north portal was approximately 7 meters below ground