Canvas


Under contract with Onni, Hall Constructors completed this 35,000 m3 excavation & shoring project using their barge facility for ocean disposal of all clean, native material. Hall was able to work with Onni to phase the excavation and allow the formwork contractor to begin early work on the back half of the site while Hall finished at the front. This meant that the first suspended slab could be poured before the detail excavation was complete.